Operation and maintenance cost estimates should be obtained from local
engineers or consultants. The difficulty here for your worksheet calculation
is in comparing an annual and continuing expense to one-time expenses (like
dam demolition). That is, how do you compare the costs of a $100,000 one-time
construction fee and a $5,000 operation and maintenance payment that will
need to be made every year for as long as the dam remains standing?
This annual cost issue will come up again with other categories
in this module, and these annual fees can be significant as they accrue
over time. Your economic worksheet will consider the economic issues of
your community as it is currently composed. As such, perhaps a consideration
of annual costs for the next 100 years unnecessarily includes expenditures
that should properly and fairly be left for future generations to weigh.
Rather than engage in other complicated forms of estimation, the suggestion
here is to pick a reasonable time frame for which your community is likely
to still be the "same" community. There is a legal basis for using 10 years
(see the Legal
Aspects module) as a reasonable time frame for your community to hold
itself liable to pay for an ongoing obligation. A hypothetical calculation
might look like this:
($5,000 annual operation and maintenance costs) x (10 years) = ($50,000 total cost estimate).
Another cost to consider is the regular “maintenance” of the impoundment. The impoundment is a receptacle for sediment that is being delivered to it by the river from the watershed. If enough sediment is trapped behind the dam, the depth of the impoundment will be greatly diminished. The depths of impoundments may have decreased so much that dredging is required to maintain its usefulness for recreation. This can be very expensive and a continual cost during the remainder of the life of the dam. For example, at the Bloomer Dam on Duncan Creek, Wisconsin, dredging was estimated to cost $3.50 per cubic yard. This equated to $553,000 for a 1-foot increase in the depth of the entire 98-acre impoundment. Maintenance costs of an impoundment are usually the result of decreased depths due to sedimentation. As the depth of an impoundment decreases, it becomes a better producer of aquatic vegetation. To maintain the recreational usefulness of the impoundment, regular weed harvesting may be needed. These costs, which will be sporadic, should also be estimated for a reasonable time frame, such as 10 years.
The operation and maintenance costs of a dam removal site will vary greatly depending on the site-specific situation and the number of amenities the area has. The annual upkeep price you arrive at will have to be adjusted in the same way that other annual and continuing expenses have been estimated in this module for inclusion in your worksheet. (See the Repair part of the Safety and Other Liabilities section of this module for more detail.)